A circular transformation for an iconic Brussels site
Texte: Joaquim Dupont Photos: Yvan Glavie

At the initiative of ULB, VUB and the Brussels-Capital Region, the former Fritz Toussaint barracks in the heart of Etterbeek have been transformed into a new sustainable, mixed-use neighbourhood designed for both the university and the wider community. The project, named Usquare and designed by EVR Architecten, BC Materials & Studies and Callebaut Architecten, stands out for its comprehensive circular approach, which highlights the heritage value of the site. The project was delivered by main contractor BPC Group, with engineering studies provided by VK architects+engineers, part of Sweco.
A comprehensive circular programme
In line with the client’s circular approach, the Usquare project primarily aimed to preserve as much as possible, particularly the three main buildings along Boulevard Général Jacques. These will house various university facilities as well as accommodation for visiting researchers. For two smaller neighbouring buildings, only the façades were retained. The project also involved a comprehensive redesign of the site, including a public park to create an open space that connects with the surrounding built environment. Finally, new access points were created, including one linking the site directly to Etterbeek station, across the boulevard.

“We put everything in place to protect the elements that were to be retained and made a huge effort to reuse materials from the demolished buildings, as well as materials sourced through other circular channels,” explains Pamela Dominguez, Project Manager at BPC Group. She adds: “This project also gave us the opportunity to establish genuine synergies between different projects under way at our company.” The Project Manager also highlighted the open-mindedness and support of the client and the architects leading the project, who were willing to make aesthetic concessions to maximise circularity.
As for new materials, the Usquare project prioritised bio-based options: hemp-lime walls, acoustic clay plaster and even shell insulation beneath the concrete slabs. “Sustainability was taken as far as possible, right down to using paints made with at least 90% natural raw materials,” confirms Pamela Dominguez.
In-depth studies deliver an exemplary result
The project partners were able to draw on the expertise of multidisciplinary consultancy VK architects+engineers, covering everything from sustainable design and building services to acoustic engineering and structural engineering. The consultancy’s teams worked closely with the various stakeholders, always through the lens of resilience, to deliver a sustainable result. “The building’s function is not entirely fixed, and it can be adapted in the future with minimal investment in materials,” explains Bram Derudder, Project Manager at VK. The site’s flexibility is also ensured through the use of demountable “box-in-box” systems.
VK’s teams also implemented various solutions to achieve this result. “The site will be supplied by a heat network to heat the VUB buildings. We also opted for a ‘light as a service’ system to meet lighting needs,” he adds.

A rewarding project
Delivering a circular project on this scale comes with many challenges. “For reclaimed bricks, for example, we had to carry out frost resistance and compression tests to make sure they met the applicable standards for their intended use. These are factors we don’t have to consider with new materials, and they make the project unpredictable. That pushes us to find new solutions and take a trial-and-error approach,” says Pamela Dominguez.
BPC Group also had the opportunity to meet new subcontractors specialising in circular construction and learn about their working methods. “For several years now, BPC Group has been working to establish itself as a trusted partner for circular construction and renovation projects. Usquare is a perfect fit with that ambition and has enabled us to further develop our expertise in this area,” adds Laurence Decroix, Communications Manager at BPC Group.
Despite the challenges encountered, the main contractor is proud to have delivered the project successfully. “Usquare shows that circular transformation and heritage restoration projects can be successfully delivered, and we hope it will serve as an example for others in the future,” she concludes.